Thursday, October 31, 2019

Economic Analysis Paper The Professional Sports Industry Essay

Economic Analysis Paper The Professional Sports Industry - Essay Example Growth of public significance of modern sports (mainly big-time sports) allows to consider the sports as a complecated process. Sports as a separate and self-developing phenomenon has not yet become an object of â€Å"classical† sports theory researching. Professionalism of sports at last quater of XX century has got the general character and now it is considered like a natural process. The events and people’s activity in professional sports attracts much attention of population of any country. Sports influences all spheres of life such as economics, poticy and culture. And touches many ethical problems of nowadays environment. It is considered that professional and big-time sports increases the state prestige, peace consolidation, and even popular sports. It is difficult to tell about the health problems which many sportsmen have. It is a fact that most of the sportsmen have serious deseases. Full-time trainings (especially for women and children), off-centred methods which include dopes and stimulators, various injuries, contests and fightings for the first place – all these things hurt morally and physically greatly. It is not a secret that very often a criminal cases take place in the professional sports industry. The sports economy has got important quantative and qualitative changes lately. The new technologies of market are in use now and the interaction looks in such a way – sports – fan, and sports – customer. The instruments and methods of management and marketing are actively used now. Along with the perfection and stirring up of the traditional instruments of influence on people (such as cost policy, advertising and quality) new trends got the impulse to development, the promotion of which became possible only with the help of Internet. A new virtual system of â€Å"new economics† began to develop. This system includes a complex of branches and groups of innovation economical activity. In structure of virtual economics of sports the

Tuesday, October 29, 2019

Abigail Williams and How She Contributed to American History Essay Example for Free

Abigail Williams and How She Contributed to American History Essay Abigail Williams was a suspicious 11 or 12 year old girl who was the leading cause of the Salem Witch Trial hysteria. There is not much background information on her, but as far as history goes, Abigail was born 1680 and lived with her Uncle Samuel Parris’ family, who was the head Reverend of Salem, Massachusetts at the time. â€Å"Although it was ordinary practice for young girls to live with relatives to learn about housewifery, we know very little about Abigail, including where she was born and who her parents were. † (Yost, 2002) In an indirect way, Abigail has contributed to American history being that she was the main cause of the Salem Witch Trial accusations. The 6th amendment of the American Constitution was highly influenced by the Salem Witch Trials. See more: Experiment on polytropic process Essay With the 6th amendment, the accused are entitled to have a witness, an attorney for their defense, and will be heard before a jury in court. The Salem Witch Trials affected the way America viewed reliable evidence used in court cases because they stopped using spectral evidence. During the Witchcraft trials, the only evidence available was hear-say information from the girls who were â€Å"afflicted.† More than 45 innocent people were killed, because the court believed Abigail and the girls without looking into further detail about the spoken witches. Nowadays, the accused are able to have a witness with them as well as some one who will look into their case and use accurate evidence to prove their innocence until proven guilty.

Sunday, October 27, 2019

Planning Issues In The Construction Industry Construction Essay

Planning Issues In The Construction Industry Construction Essay Construction is an everlasting activity across the globe. Its profitability like of any other business fluctuates according to the law of demand and supply. In most countries, construction activity constitutes 6-9% of the gross domestic product (GDP) and constitutes more than half of the fixed capital formation as infrastructure and public utilities capital works required for economic development. Construction activity contributes to the economic development of a country. The GDP per capita and the investment in the construction per capita generally follow a straight line relationship, that is construction activity increases with the increase in per capita income. Construction projects are intricate and time-consuming tasks. For the total success of any particular project a wide chain of specialized services is necessary for the timely completion of the project. During the construction process, itself even a project of small or medium proportions requires many attributes, materials a nd involves many different types of operations. The assembly process must follow a natural order of events that, in total combination, constitutes a complicated pattern of individual time requirements and restrictive sequential relationships among the many segments of the structure (Project Quality Management in Construction, K. Lambrou, G.J. Besseris and C. Alafodimos, MSc in Quality Management, TEI of Piraeus and University of Aisley).Mismanagement of resources has become a prevalent problem in many construction firms. This mismanagement of resources contributes to numerous construction firms ineffectiveness and frequent failures each year. Hence, it is necessary to take appropriate steps and follow the process to improvise the output of construction industry by using proper planning methods and techniques. This can be done through adoption of modern and improvised planning techniques in construction industry such as CPM, PERT, Supply Chain Management etc, which will be discussed in detail in main dissertation work. In the literature review of planning issues in construction industry, different aspects of social-cultural-economic importance of planning and modern planning techniques has been highlighted. This dissertation focuses on analyzing the major hindrances caused by the positive and negative issues in planning and execution phase of the project. 2. Background Planning is a key ingredient in the successful completion of any construction project. It provides the road map for the project to follow and the milestones by which its progress is measured. To understand the loopholes in the planning process it is necessary to dismantle the planning objectives, so that all the aspects regarding the project could be thoroughly capitalized. Four planning objectives which characterize the whole of the planning process are execution of work, coordination of all the activities, control over the materials and manpower and forecasting. Safety is a major concern to every successful construction project because of humanitarian concern for the workers and the cost ramifications of a poor safety record. Major construction firms had proposed the usage of network planning techniques, mainly because of owners demand. The relationship between project planning and construction safety is sometimes subtle, and the impact it has on the project is not as readily apparent as the importance of planning and safety as separate entities. A comprehensive planning and scheduling specification system can aid in the planning of job sequence, financial needs, workforce needs, material needs, and equipment needs. It also can aid the scheduling of actual activity start or completion and provide feedback to control the schedule, cost, and use of resources. A critical step in the execution of any construction project is the selection of planning and scheduling specification clauses to be included in the construction contract. Numerous project characteristics should be taken into account when determining which planning and scheduling clauses to be included. Project is a mission, undertaken to create a unique facility, product or services within the specified scope, quality, time and costs. With the emerging global opportunities, projects cross geographical boundaries, corporate channels, traditional systems and cultural diversities. The knowledge areas needed to manage such projects comprise project management techniques, general management practices and technology-related subjects. The project management techniques of planning, scheduling and controlling are the tools and devices that bind the subjects knowledge areas. These techniques can be applied to all types of projects. This research focuses on the application of all these techniques in the construction industry. It is widely recognized that effective planning can play a major role in the success of projects. Whether project success is based on the traditional measure of time, cost and quality or newer measures of critical success factors (Westerveld, 2003), effective planning can also contribute to the prevention of accidents and ill health of site personnel (Duff and Suraji, 2000; HSE, 2003). These objectives become increasingly difficult to achieve, however, in construction projects. Construction sites can be extremely busy places where the working environment is ever changing. Unfortunately, in addition to this, the construction industry tends to be under resourced and under planned in relation to other industries (Egan, 1998), which can lead to a crisis management approach to production risk, a feature of construction culture which can impact heavily on health and safety. Despite this, activities requiring intensive planning as those required in a temporary rail possession, almost invari ably run smoothly. There is little chance of an unsafe incident, due to the heightened risk awareness resulting from the meticulous planning. 3. Aims and Objectives To study various minute details affecting the process of planning. The objective of this research is to assess the modern methods of planning and scheduling a construction contracts which can be applied in todays construction industry and to also discuss the issues involved in the application of those tools. To compare and analyze a planning strategy which has a solution for various issues in the planning process. 4. Research Methodology The research methodology is the approach through which the researcher collects the data useful for the chosen topic and then the analysis is done on the basis of that. In my dissertation, I will be using qualitative research as means to study planning and scheduling in construction contracts. 5. Scope and Limitations of Dissertation The limitations of the dissertation are: This research targets only construction industry, hence the results cannot be implied on the others sectors. This analysis will be done for Indian and UK industry. However, the study done on India and UK is not necessary applicable for other nations as well as because of cultural differences. Planning techniques for different countries is different which adds to more misery. The unavailability of proper planning and management techniques, which could possibly solve the issues of planning even when proper resources are not available. Construction Industry has flourished domestically as well as globally over the years. Economic development of any particular country also largely depends upon the construction projects. Major factors that affect the overall result of any project would be size, complexity, quality, productivity, completion time and cost. These factors would be achieved only when proper planning is done, which forms the base of construction management. A project plan is always formulated during the planning phase. Planning in its broader perspective, involves advance thinking as to what is to be done, what are the activities, how it is to be done, when it is to be done, where it is to be done, what is needed to do it, who is to do it and to ensure that it done. A project plan would be adversely affected if cost overruns and delays take place. The effect of past construction experience, on the quality of management in general and on planning effectiveness in particular, is addressed only rarely in const ruction-management research; the few studies doing so explicitly are in agreement with the findings of the present study. NEDO (Faster 1983) reports the contractors inexperience in similar projects as a major source of difficulty in construction [Faster building for industry (1983). NEDO-Building EDC, National Economic Development Office, London, England.]. All the perseverance put into the invention of new techniques did not gave the satisfying results in the construction planning sector (Choudhury 1981, Mason 1984, Morton 1983). Sometimes people fail to recognize the difference between planning and scheduling. Progress in the usage of new computer techniques has resulted in the misconception of standardization of project scheduling. Projects have been a part of our society for quite a long era. Indication of total efficiency would be seen by completing project on time, but construction process is subjected to too many fluctuations and unforeseeable factors which results from many sources (Sadi. A. Assaf, Sadiq Al-Hejji, (2005)). Construction organization lives in the ever-changing and their effectiveness depends on their ability to adapt to new demands and opportunities. This industry needs to adjust itself to the changes occurring in its working environment in order to become effective. Construction projects are intricate and time-consuming tasks. The total development of a project normally consists of several phases requiring a diverse range of specialized services. In progressing form initial planning to project completion, the typical project passes through successive distinct stages that demand inputs from such disparate groups as financial organizations, government agencies, engineers, architects, lawyers, surety companies, contractors, and building trade-persons. Most challenging part of these modern techniques is implementing these methods to achieve a particular goal or task. Construction Industry faces a lot of problems because of the working patterns and inefficient planning techniques to reach to complete a particular function. Following the modern planning techniques reduces the dilapidation of resources and economically strengthens the company. A constant focus should be given on the improvisation techniques which include mutually collaborating one or more techniques which would lead to a profitable project and reduce the loss due poor performance and cost overruns. The constructions industry in India and UK has realized the importance of the proper usage of modern planning techniques which has improvised the margins of profits and truncate the overall project cost. In India planning is an open process (Planning in India RICHARD S. ECKAUS MASSACHUSETTS INSTITUTE OF TECHNOLOGY ).If design completion is not done at proper time it would prove to be costly, as it would lead to construction delays. In India a prevalent method to planning is not sufficient as there are many situations which includes Limitation or inexpertness of human beings in there respective fields (Human Errors). Influence of external factors beyond human control (E.g. Natural Hazards: this could have an adverse effect on the planning process). The external components interact with the construction firm from outside of the organizations environment. Such external components are material suppliers, financial institutions, and surety companies, end users of products, owners, and architects. The project is also influenced by external causes due to scarce availability of resources in the market (Techniques and Technology). The project covers important framework of an integral system; therefore considerable economic or technical consequence could result from faulty usage. (An approach to planning and control of advanced projects Giorgio Caroni, Roland0 Matteelli and Alfred0 Berti) In order to have a competitive edge over other construction companies, perfectly planning techniques should be used. Main Body CASE STUDY: Even though India is one of the developing countries the approach towards planning is comparatively more advanced as compared to other developing countries. (Planning in India, RICHARD S. ECKAUS, MASSACHUSETTS INSTITUTE OF TECHNOLOGY). In India, for small scale project ranging between 1million £-10million £ specific planning techniques cannot be implemented, as a lot of unavoidable problems usually arise due to many reasons. Comprehensive survey of the location of the project clearly marks the project area and its boundaries. Soil investigation is to be done to ascertain the soil strength so as to decide the type and other specific details of the foundation. Depending upon the soil investigation reports, finalize the type of foundation i.e., pile foundation or open foundation up to hard strata strength. Necessary approvals, clearances, no objection for all the concerned government departments, local or self governing authorities should be obtained before starting the project. To ascertain whether any public utility service lines like Water pipe lines, sewage pipe lines, electrical cables or over head lines, telephone line or any other Public/Private items or assets are crossing /passing through the designated project area. Specific measures must be taken to relocate the service lines or public assets before starting the project. Drawings incorporating all the specific details, dimensions and other specifications must be accurate and must be got approved from all the relevant authorities before starting the work If any of the above fundamental issues are neglected at the planning stage, you are steadily heading for a project period over run and project cost overrun. TYPICAL CASE STUDIES FROM INDIA BUILDING PROJECT OF CBI(CENTRAL BEAURAU OF INVESTIGATION) BUILDING 1) Name of Work : Construction of Administrative Building including all infrastructure Amenities for C.I.D Pune. at Pune 2) Client : Maharashtra State Police Housing Welfare Corporation. Limited, Mumbai 3) Tender Work Order No : PHC/TB/CID PUNE/1152/2005 Dated 15.07.2005 from General Manager 4) Contractor : M/s. Deepa Engineers, 42, Welfare Chambers, 1st Floor, Sector-17, Vashi, Navi Mumbai 400 705 5) Architect : M/s. Arc-Aids. Pune 6) P.M.C : M/s PP Ventures, Pune 7) Tendered Amount : 5, 43, 04,161/- 8) Date of Starting : 02.09.2005 9) Stipulated period of completion : 31.05.2007 10) Area as per tender : 5483.57 Sq.Mtr 11) Area as per actual construction : 7217.19 Sq.Mtr. Including Common Facility. 12) Common Facility Area : 109Sq.Mtr 1) Septic Tank = 36 Sq.Mtr 2) Meter Room = 19 Sq.Mtr 3) Pump House = 54 Sq. Mtr 13 Area Constructed : 7108.19 Sq.Mtr (7217.19-109 = 7108.19 Sq.Mtr) 14) Actual date of completion/ : 31.03.2009 Taking over 10.07.2009 15) Difference in Area : 1669.62 Sq.Mtr. 16) R.A. Bill No. 21st (pending) : 30,70,629.00 17) Final Bill yet pending : 26,01,169.00 18) Security Deposit : 13,57,604.00 19) Retention money deducted From 20th R.A. Bill : 1,38,747.00 20) Retention money deducted From 21th R.A. Bill : 1,52,052.00 21) Extra Items Amount : 1,83,210.00 22) Inauguration Expenditure : 3,10,000.00 23) Bank Guarantee En cashed : 13,57,604.00 Total Claims overdue : 91,71,015.00 + Difference in Constructed Area amount Conclusion Departmental interaction between various service agencies of the state, like the police housing Department and PUNE Municipal Corporation must have been initiated at the planning stage of the tender itself. Though the project is commissioned successfully on 10th July-2009 and the C.B.I has occupied the Administrative Building, with all the proposed amenities the Contractor has suffered huge financial losses. Presently the case is under arbitration Justification for the delay of work 1) M/s. Arc-Aids, (Architect) M/s. PP Ventures, Pune (PMC) were new to the department lack of coordination between them with Police Housing and the contractor resulting in bad delay in furnishing the requisite drawings and other relevant details for the timely execution of the work. 2) Delay due to the shifting of approx One Meter Diameter Water pipe line of Pune municipal corporation which was not shown in the layout drawing of the tender, passing through the site feeding water supply to Pune City Delay 10 Months. The work was coordinated by Deepa Engineers and executed by Pune Municipal Corporation without any financial obligations to PHC. Drawings must incorporate all the details accurately, after carrying out proper survey of the project area. 3) Non releasing of the payments in time by holding of Running Bills payment by imposing heavy penalty as given below, which was against the terms conditions of the Tender, since the delay was caused by reasons beyond the responsibility control of the contractor Sr.No. Particulars No. of days Amount to be recovered from Bill in Rs. 1 Rs. 1000/-per day w.e.f. 1/6/07 to 15.01/08 229 2,29,000/- 2 Rs. 5000/-per day w.e.f. 16/01/08 to 15/02/08 31 1,55,000/- 3 Rs. 10000/-per day w.e.f. 16/02/08 to 12/05/08 87 8,70,000/- 4 Rs. 15000/-per day w.e.f. 13/5/08 to 30/06/08 49 7,35,000/- 5 Rs. 65000/-per day w.e.f. 1/7/08 to 10/07/09 375 2,43,75,000/- Total 771 2,63,64,000/- This holding of payment was waived and released by Hon. S.S. Virk after joining as M.D. of Police Housing Corporation and assured that the penalty will be waived and the difference in area constructed will be consider after completing the work. Accordingly the work is restarted and completed on 31.03.2009 and handed over on 10.07.2009. Month wise requirement of funds if predicted during the plannings stage itself, the payment schedule flow of money will not be hampered. B) Name of Project: 1) Construction of three storeyed of 300 seated Post Graduate Hostel including internal Water supply, Sanitary installation, Drainage wok and internal electrification work for Vishweshwarayya National Institute of Technology, Nagpur, India Name of Contractor : M/s. DEEPA ENGINEERS, 42, WELFARE CHAMBERS, 1ST FLOOR, SECTOR-17, VASHI, NAVI MUMBAI Estimated Cost : 5,33,56,856/- Tendered Amount : 9,34,63,099.00 Time allowed : 16 Months including monsoon Period Commencement Date : 12.07.2007 Stipulated date of completion : 11.11.2008 Security Deposit : 46,73,155.00 (Bank Guarantee) Project Management : Central Public Works Department, Superintending Engineer, Central Circle, Nagpur. Architects : do B) Name of Project: Construction of Additional storey (100 seated) over proposed 300 seated Post Graduate Hostel at Vishweshwarayya National Institute of Technology, Nagpur. Name of Contractor : M/s. DEEPA ENGINEERS, 42, WELFARE CHAMBERS, 1ST FLOOR, SECTOR-17, VASHI, NAVI MUMBAI Estimated Cost : 1,78,70,130.00 Tendered Amount : 2,36,39,902.00 Commencement Date : 28.11.2008 Stipulated date of completion : 27.05.2009 Security Deposit : 11,82,000.00 (Bank Guarantee) Time allowed : 6 Months Project Management : Central Public Works Department, Superintending Engineer, Central Circle, Nagpur. Architects : do Actual date of Completion : 31.03.2010 Parameter adopted for mix design for RCC works Ready Mix Concrete Nominal maximum size of aggregate : 20 mm angular as per C.P.W.D. description Degree of quality control : Good Type of Exposure : Moderate Maximum water cement Ratio : 0.50 Cement Content : 410/Kg/cum of concrete Type of Cement used : OPC 43 grade Conforming to IS: 8112 Sand : Coarse sand as per CPWD Specification Approved Admixtures conforming to I.S. 9103 permitted Fly wash shall not be used in R.C.C The Contractor shall submit the Mix Design Report from Approved Laboratory and get it approved from the Engineer-in-Charge Causes for the delay in completion of the project. Inaccurate Soil Investigation Report. The Original depth of Excavation, for Foundation fixed as 5ft(1.52 m) as per tender. At the time of actual execution the depth upto loft which resulted in huge quantity variation in excavation, quantity of steel and other items necessitating further approvals from all competent authorities. This project cost overrun and period overrun could have been avoided if proper soil investigation was carried out before tendering A Major defect in planning was the decision to have an additional floor with 100 seats after the completion of the hostel building up to 3rd floor by the contractor. The right decision to have a Four storied 400 seated Hostel building initially would have saved the Project period by at least 4 months Also there could have been a saving of the total Project cost by at least 03 % TABLE OF MILESTONE (S) CASE B(1) S. No. Financial Progress Time allowed (from date of start) Amount to be withheld in case of non achievement of milestone 1 All P.C.C. and brick works up to plinth level 120 days In the event of not achieving the necessary progress as assessed 1% of the tendered value of work will be withheld for failure of each milestones 2 Complete R.C.C structure up to terrace level 240 days 3 All brick work , flooring, internal plaster, fixing of door frames and windows etc along with all related items 355 days 4 Water proofing to terrace slab, external plaster and painting, fixing of all electrical and water supply, sanitary fitting etc. complete along with handing over of building including external service connections complete. 16 months TABLE OF MILESTONE (S) CASE B(2) S. No. Physical Progress Time allowed (from date of start) Amount to be withheld in case of non achievement of milestone 1 All R.C.C. Columns 30 days In the event of not achieving the necessary progress as assessed 1% of the tendered value of work will be withheld for failure of each milestones 2 Complete R.C.C and brick work up to terrace level 90 days 3 All brick work , flooring, internal plaster, fixing of door frames and windows etc along with all related items 150 days 4 External plaster and painting, fixing of all water supply, sanitary fitting etc. complete along with handing over of building including external service connections complete. 6 months Results from the Case Study: IN GENERAL VIEWS Table 1 List of causes of delay which may affect the overall planning is categorized below (Causes of delay in large construction projects, Sadi A. Assaf *, Sadiq Al-Hejji) No. of. Causes of delay affecting the planning process Group 1 The Original contract duration is very short Project 2 Disputes between various parts Project 3 Inadequate definition of substantial completion Project 4 Ineffective delay penalties Project 5 Type of construction contract (Lump sum contract, construction only,) Project 6 Type of project bidding and award ( lowest bidder) Project 7 Delay in payments by the owner Owner 8 Delay to furnish the site to the contractor by the owner Owner 9 Revision orders by the owner during construction phase Owner 10 Late in changing and approving the design documents by the owner Owner 11 Delay in approval of drawings and the sample materials Owner 12 Improper communication by owner and other parties Owner 13 Unwillingness to make proper decisions Owner 14 Disagreements occurring between joint-ownership of the project Owner 15 Absence of incentives for contractor for finishing the work ahead of schedule Owner 16 Discontinuation of work by owner Owner 17 Financial problems faced by contractor Contractor 18 Problems in sub-contractors schedule in execution work Contractor 19 Alterations during construction due to some minor errors Contractor 20 Affray between contractor and other parties Contractor 21 Inappropriate site management by the contractor Contractor 22 Inappropriate communication by contractor with other parties Contractor 23 Poor planning of project by the contractor Contractor 24 Improper construction techniques implemented by contractor Contractor 25 Postponement in sub-contractors work Contractor 26 Inadequate standard of work by contractor Contractor 27 Periodic changes of sub-contractors Contractor 28 Poor qualification of technical staff Contractor 29 Mobilization problems at site Contractor 30 Postponement in inspection and testing by consultant Consultant 31 Delays in the approval of major changes in the scope of work by consultant Consultant 32 Inflexibility shown by the consultant Consultant 33 Improper coordination between consultant and other parties Consultant 34 Slow to review and approve the documents by the consultant Consultant 35 Issues between the consultant and the design engineer Consultant 36 Inadequate experience of consultant Consultant 37 Mistakes in the design documents Design 38 Delay in delivering the design documents Design 39 Imperfect details in drawings Design 40 Complications in understanding of the project design Design 41 Incomplete data collection survey before design Design 42 Confusion in owners requirements by design engineer Design 43 Insufficient design-team experience Design 44 Low amount of usage of advanced engineering design software Design 45 Shortage of construction materials in market Materials 46 Alterations in the type of materials and specifications during the construction Materials 47 Immobilization of material Materials 48 Damage of sorted material while they are needed urgently Materials 49 Delay in manufacturing special building materials Materials 50 Late procurement of materials Materials 51 Late in selection of finishing materials due to availability of many types in market Materials 52 Equipment breakdowns Equipment 53 Shortage of equipment Equipment 54 Low level of equipment-operators skill Equipment Equipment 55 Lack of high-technology mechanical equipment Equipment 56 Shortage of labours Labours 57 Unqualified workforces Labours No. Causes of delay Group Labours 58 Nationality of labours Labours 59 Low productivity level of labours Labours 60 Personal conflicts among labours Labours 61 Effects of subsurface conditions (e.g., soil, high water table, etc.) External 62 Delay in obtaining permits from municipality External 63 Hot weather effect on construction activities External 64 Rain effect on construction activities External 65 Unavailability of utilities in site (such as, water, electricity, telephone, etc.) External 66 Effect of social and cultural factors External 67 Traffic control and restriction at job site External 68 Accident during construction External 69 Differing site (ground) conditions External 70 Changes in government regulations and laws External 71 Holding up the work from the important utilities i.e., water, electricity etc External 72 Final inspection has been delayed by a third party External Literature Review: Definitions and Concepts of Planning and Planning issues Planning can be defined as any one of the following: 1. A decision-making process. 2. A process of anticipatory decision-making to decide what and/or how to perform actions due at some point in the future. 3. A process of integrating interdependent decisions into a system of decisions. 4. A hierarchical process evolving from general guidelines to objectives, to the elaboration of means and constraints that lead to a detailed course of action. 5. A process that includes part or all of a chain of activities comprising information search and analysis, development and design of alternatives, analysis and evaluation of alternatives and choice making. 6. The systematic employment of procedures (standardized and formal to varying degrees). 7. Documented presentation, in the form of plans. (Is construction project planning really doing its job? A critical examination of focus, role and process, A. Laufera; R. L. Tucker, Department of Construction Management, Technion IIT, Haifa, Israel b Construction Industry, Institute, The University of Texas at Austin, TX, USA) Social-Cultural-Economic Importance of Planning(POSTIVE AND NEGATIVE) Cultural Aspects: (International Measurement of the Economic and Social Importance of Culture, Prepared by John C. Gordon and Helen Beilby-Orrin) . The Australian statistical office

Friday, October 25, 2019

telecommuting :: essays research papers

Telecommuting Telecommuting starts with the lower level of the working class workers but with the success it has had it’s rapidly moving towards the executive level. There are two form of telecommuting the employers use today, one is home telecommuting which is a work arrangement the most people do this is working from home with a computer terminal utilizing today’s current technology by transmitting data and documents while working from home and maintaining a close contact with co-workers, managers, through the use of email, internet (instant messenger), and telephone and fax machines as well. Video conferencing using web cameras can also be an effective tool for telecommuting in order to help enhance for its employees and executives. The other form of telecommuting is center based telecommuting that involves the use of office space close to home where employees works without direct supervision, commute travel is still reduced and some of the disadvantages of home offices are remove d. Home telecommuting plugs into everything that is happening at the office just as if they were at the office. By opening your networks to the public and allowing your information available to the internet Co-works will have to access your information available with many different types of home equipment needed for home telecommuting that can be a little expensive at first to get started. Some of the different equipment that is needed is a computer with fax and scanner so proper communications are available, phone, high speed internet connection, a desk, file cabinets, and a web camera with an internet messenger along with video conferencing software. There are many advantages for companies today to use telecommuters in their day to day business operations. This allows business’s to cut corners and save money so that way more money can be spent on other projects which will make more of a profit, and help reduce the costs for gas and travel expense for employees who travel a lot. They also have a larger audience of applicants to choose from which allows them to sort out the for specific skill or education for jobs they are trying fill which later will help contribute to an increase productivity and promoting a happier staff giving more time to workers for family time at home. By using telecommuters who will be actually working at the office perhaps once a weak or so helps save on realistic costs because employees who work at home do not need offices and when they are at the office they can share cubicles with other telecommuters promoting less space needed to lease.

Thursday, October 24, 2019

Plight of U.S. Farmers and Workers

The structure and style of politics in the late nineteenth century were evolving based on what party held power in our government. Social, religious, ethnic and regional factors determined party ties but third parties were emerging. Consider the conditions In America on the eve of the 20th Century.Write a minimum of two paragraphs for the following discussion prompt: What problems did U. S. Farmers and workers face In the sass and how did they try to solve them? The prices of the crops were falling and were at an low and there wasn't end in sight due to things as of the weather and other death rising factors like materials being over produced in the North and the East while the West and the South struggled. Goldfield, 2014) This added so much hardship for so many farmers that most could not afford to pay for the cost for using the railroad to ship their goods and as crops failed, It made It Impossible for the farmers to pay off their debts and many farmers lost their farms, lands, cr ops and all other sources of income forcing many onto sharecropping, (Goldfield, 2014) This led a need for change and people started looking for other options.They pleaded for help from the Government, but showing that they cared little to none and by doing nothing to help the people left planning and coming up with their own solution, â€Å"Farmers Alliance† (Goldfield, 2014) This was a big playoff with so much against such Like many to most people were still separated by race and neither could grow past the pettiness to try to think of even helping each there with such preformed alliance and even with such like economic and political reform smoothly for most more deeper separation based on race.Made this a long sighted has black farmers, including the leaders that were colored and section of the Farmers Alliance were killed an of the Farmers Alliance that came followed by depression and it was one out for themselves. The Government had no control with more violence that rul ed the people and the streets. The railroad had over expended, hundreds of banks closed, along with thousands of businesses. (Goldfield, 2014) Since o much money stopped flowing at one time there was no way for the economy to come back to life.In order for the depression to end, the people needed jobs and they needed farms that could support the Nation. They had to have banks that could provide lines of credit to get the Nation Jump started. With the fall of the economy In other Nations only added to our turmoil and they cost too much to use as export markets. Which Is reason exporting trade system came right with or after. References Goldfield, D. , Abbot, C. Anderson, V. Reselling,J. Argentines, P, Barney (2014).

Tuesday, October 22, 2019

A local conflict Essay

Q) With reference to a local conflict over the use of a resource that you have studied, discuss the extent to which all interest groups involved can be satisfied with its outcome. (40) The local conflict I have studied was the expansion of Heathrow airport, although the conflict itself ended in 2010 when it was legally resolved. However there are still effects that were created from the plans to expand Heathrow that have upset many different groups. In this essay I will discuss how the groups involved were either satisfied or dissatisfied with the outcome. There was a debate to whether or not the expansion at Heathrow was necessary. Here BAA (the airports directing company) pointed out that Heathrow was currently operating at 99.2% capacity utilisation meaning that even small incidents would create major delays, such as the ability of Heathrow to cope in extreme winter conditions such as snow. But the Greater London Authority and Hillingdon council argued saying there were alternativ es such as expanding Gatwick airport. Labour parliament also intervened stating the huge increase in passengers should be met by London’s most efficient and largest airport should be developed into the UK’s air hub. However the conservative party suggested more alternatives such as improving rail infrastructure to allow extra capacity to spread to other airports such as Manchester. This would benefit the north of England especially with the struggling economy. Arguments then arose over the impacts that would come from the expansion of Heathrow and there were many mixed attitudes towards this. A positive outcome economically would be that 140,000 new jobs would be created meaning that more people would be earning a decent wage paying taxes that would contribute to the government in funding public services such as hospitals. And if the expansion didn’t go ahead then it was estimated the UK would lose potentially  £4.5 billion GDP growth and  £1.6 billion of its existing GDP to other nations around the world. But the protest groups ‘Plane Stupid’ said that jobs would only benefit the south east as this is where Heathrow is located, it was also pointed out that the GDP figures are miniscule when compared to the UKs total GDP of  £2.435 trillion. In terms of the environment, the labour government at the time presented schemes whereby extra greenhouse emissions would be offset. This included involvement in the EUs new Carbon Permit Trading Scheme. However many environmental groups and  charities argued against this. Greenpeace produced information showing that Heathrow’s post-expansion carbon footprint would be a similar size to that of Kenya’s. The National Trust pointed out that regardless of whether CO2 was being offset around the UK, London air quality would fall. Also, the impacts on local communities came into question. A village on the expansion site known as Sipson would be destroyed if the expansion of Heathrow was granted. This would involve 700 homes being demolished as well as several a listed buildings. BAA claimed it would relocate and reimburse the whole community displaced. They also said they would not destroy but in fact repair and maintain the listed buildings on the site. However Sipson village council, the Greater London Authority and the conservative party argued against this. They stated that significant proportions of Greenbelt land would be destroyed and the sound levels in the area wou ld expand by several km2. In January 2009 Heathrow’s proposal for expansion was granted by the Labour Government. But this was put to a standstill as the demonstration groups opposing the plans for Heathrow appealed the decision to the Higher Court. It took a whole year of a legal battle but it was decided eventually in March 2010 that the Labour government’s decision was invalid and it was placed under review. That year in the general election the Conservatives and Lib Dems came to power and cancelled all the plans and proposals of extending Heathrow. With this outcome many groups were satisfied such as the Royal Society for the protection of Birds as the habitat of many birds around the airport shall not undergo any more destruction. However it is notable that the expansion won’t occur in the medium term. This is due to the whole process shall have to be reran if the plans are to risen again. Therefore it could be argued that in the short term the opposition groups will be satisfied. But in the long term the decision may be overturned and these groups left dissatisfied. For example Sipson Village Council are now being brought into another conflict as an alternative to the expansion of Heathrow the government have begun developing the HS2 as an infrastructure project. Supposedly it will link up with Heathrow, meaning the land will be built upon again destroying thousands of homes in the process. So now local communities are having to campaign in another conflict leaving them still dissatisfied. In conclusion, protest groups have been awarded for their hard work and efforts in avoiding the plans for Heathrow expansion going  ahead which has been very satisfying. But in the long term more problems have arisen as the HS2 is said to be in motion which would just cause the same problems to local communities. It seems that no matter what the decision some groups will always have different feelings towards them of satisfaction and dissatisfaction.